AUSTRALIAN COMPETITION TRIBUNAL

 

Application by EnergyAustralia and Others [2009] ACompT 8



CORRIGENDUM


File No 2 of 2009


RE:     APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A DISTRIBUTION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO ENERGYAUSTRALIA PURSUANT TO CLAUSE 6.11.1 OF APPENDIX 1 OF CHAPTER 11 OF THE NATIONAL ELECTRICITY RULES

 

BY:     ENERGYAUSTRALIA

Applicant

 

AND:              SOUTHERN SYDNEY REGIONAL ORGANISATION OF COUNCILS

 

Intervener

 

 

File No 3 of 2009

 

RE:     APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A TRANSMISSION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO TRANSGRID PURSUANT TO CLAUSE 6A.13.1 OF CHAPTER 6A OF THE NATIONAL ELECTRICITY RULES

 

BY:     TRANSGRID

Applicant

 

File No 4 of 2009

 

RE:     APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A DISTRIBUTION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO INTERGRAL ENERGY PURSUANT TO CLAUSE 6.11.1 OF APPENDIX 1 OF CHAPTER 11 OF THE NATIONAL ELECTRICITY RULES

 

BY:     INTEGRAL ENERGY

Applicant

 

File No 5 of 2009

 

RE:     APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A TRANSMISSION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO TRANSEND PURSUANT TO CLAUSE 6A.13.1 OF CHAPTER 6A OF THE NATIONAL ELECTRICITY RULES

 

BY:     TRANSEND

Applicant

 

AND:  Nyrstar Australia Pty Ltd

Intervener

 

 

File No 6 of 2009

 

RE:     APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A DISTRIBUTION/TRANSMISSION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO COUNTRY ENERGY PURSUANT TO CLAUSE 6.11.1 OF APPENDIX 1 OF CHAPTER 11 OF THE NATIONAL ELECTRICITY RULES

 

BY:     COUNTRY ENERGY

Applicant

 

 

JUSTICE MIDDLETON (DEPUTY PRESIDENT), MR R DAVEY AND MR R Shogren

12 november 2009 (CORRIGENDUM DATED 1 DECEMBER 2009)

MELBOURNE (HEARD IN SYDNEY)




IN THE AUSTRALIAN COMPETITION TRIBUNAL

 

 

File No 2 of 2009

RE:

APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A DISTRIBUTION/TRANSMISSION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO ENERGYAUSTRALIA PURSUANT TO CLAUSE 6.11.1 OF APPENDIX 1 OF CHAPTER 11 OF THE NATIONAL ELECTRICITY RULES

 

BY:

ENERGYAUSTRALIA

 

Applicant

AND

SOUTHERN SYDNEY REGIONAL ORGANISATION OF COUNCILS

 

Intervener

 

 

 

File No 3 of 2009

 

RE:

APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A TRANSMISSION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO TRANSGRID PURSUANT TO CLAUSE 6A.13.1 OF CHAPTER 6A OF THE NATIONAL ELECTRICITY RULES

 

By:

TRANSGRID

 

Applicant

 

 

 

File No 4 of 2009

RE:

APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A DISTRIBUTION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO INTERGRAL ENERGY PURSUANT TO CLAUSE 6.11.1 OF APPENDIX 1 OF CHAPTER 11 OF THE NATIONAL ELECTRICITY RULES

 

BY:

INTEGRAL ENERGY

 

Applicant

 

 

 

File No 5 of 2009

 

RE:

APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A TRANSMISSION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO TRANSEND PURSUANT TO CLAUSE 6A.13.1 OF CHAPTER 6A OF THE NATIONAL ELECTRICITY RULES

 

By:

TRANSEND

 

Applicant

AND

NYRSTAR AUSTRALIA PTY LTD

 

Intervener

 

 

 

File No 6 of 2009

 

RE:

APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A DISTRIBUTION/TRANSMISSION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO COUNTRY ENERGY PURSUANT TO CLAUSE 6.11.1 OF APPENDIX 1 OF CHAPTER 11 OF THE NATIONAL ELECTRICITY RULES

 

By:

COUNTRY ENERGY

 

Applicant

 

the Tribunal:

JUSTICE MIDDLETON (DEPUTY PRESIDENT),

MR R DAVEY AND MR R Shogren

DATE:

12 November 2009

PLACE:

MELBOURNE (HEARD IN SYDNEY)


corrigendum

1                     Paragraph 25 should read “Ch 6A” and not “Ch 6” of the Rules.

2                     Paragraph 115 should read “5 September 2008” and not “5 September 2009”

3                     Paragraph 117 should read “5 September 2008” and not “5 September 2009”.

4                     The appearances should read

·                    Counsel for the Australian Energy Regulator:  Mr P Hanks QC with Mr P Gray, Mr P Wallis and “Dr V Priskich” not “Dr V Prisich”.

·                    Counsel for Energy Australia:  Mr J T Gleeson SC, with Mr P Brereton SC, Dr R C A Higgins and Ms A Rao

·                    Solicitor for Energy Australia:  Gilbert + Tobin.

·                    Counsel for Integral Energy not “Intergral Energy”.

·                    Solicitor for Integral Energy not “Intergral Energy”.

 

 

I certify that the preceding four [4] numbered paragraphs are a true copy of the Corrigendum to the Reason for Determination herein of the Honourable Justice Middleton (Deputy President), Mr R Davey and Mr R Shogren.



Associate:


Dated:         1 December 2009