2012 Decisions

  1. Application by DBNGP (WA) Transmission Pty Ltd (No 3) [2012] ACompT 14
    ACT 2 of 2012

    COMPETITION LAW - review of determination by the Economic Regulation Authority of Western Australia (ERA) - whether the ERA made reviewable errors in making Access Arrangement Decision - in particular: ; whether the ERA applied NGR rule 87 correctly - whether NGR rule 87(1) requires the ERA to go beyond the figure determined in accordance with NGR …

    26 Jul 2012 MANSFIELD J (PRESIDENT) ; MR R DAVEY (MEMBER) ; PROFESSOR D ROUND (MEMBER)

  2. Football Queensland Limited [2012] ACompT 15

    NOTIFICATION OF EXCLUSIVE DEALING – withdrawal of notification by Australian Competition and Consumer Commission under s 93(3) of the Competition and Consumer Act 2010 – application to Australian Competition Tribunal for review of decision – review fixed for hearing – application for leave to withdraw application for review – procedural power of…

    25 Jul 2012 MANSFIELD J (PRESIDENT)

  3. Application by Alinta Sales Pty Ltd (No 2) [2012] ACompT 13
    ACT 2 of 2011

    COMPETITION LAW - review of determination by the Economic Regulation Authority of Western Australia (the ERA) - whether the ERA made reviewable error in determining tariff increases - whether the ERA required to consider impact of tariff increase on Applicant - whether the ERA considered impact of tariff increase on Applicant - whether the ERA…

    8 Jun 2012 MANSFIELD J (PRESIDENT), MR R DAVEY (MEMBER), PROFESSOR D ROUND (MEMBER)

  4. Application by WA Gas Networks Pty Ltd (No 3) [2012] ACompT 12
    ACT 3 of 2011

    COMPETITION LAW - review of determination by the Economic Regulation Authority of Western Australia (ERA) - whether ERA made reviewable errors in making Access Arrangement Decision - in particular ; whether ERA applied NGR rule 87 correctly - whether NGR rule 87(1) requires the ERA to go beyond the figure determined in accordance with NGR rule…

    8 Jun 2012 MANSFIELD J (PRESIDENT) ; MR R DAVEY (MEMBER) ; PROFESSOR D ROUND (MEMBER)

  5. Appeal by SPI Electricity Pty Ltd [2012] ACompT 11
    ACT 9 OF 2011

    COMPETITION LAW – review of determination by the Australian Energy Regulator (AER) – determination of budgets for the roll out of ‘advanced metering infrastructure’ in Victoria – whether AER made error of fact in a material respect – whether components of forecast expenditure “prudent” – whether substantial departure from the commercial standard…

    26 Apr 2012 MANSFIELD J (PRESIDENT), MR ROD SHOGREN, PROFESSOR KEVIN DAVIS

  6. Application by DBNGP (WA) Transmission Pty Ltd (No 2) [2012] ACompT 10

    5 Apr 2012 JUSTICE MANSFIELD (PRESIDENT)

  7. Application by United Energy Distribution Pty Limited (No 2) [2012] ACompT 8
    ACT 6 of 2010 ; ACT 7 of 2010 ; ACT 8 of 2010 ; ACT 9 of 2010 ; ACT 10 of 2010

    Practice & procedure

    5 Apr 2012 FOSTER J (DEPUTY PRESIDENT), MR G LATTA AM AND PROFESSOR D ROUND

  8. Application by Co-operative Bulk Handling Limited (No 2) [2012] ACompT 9

    Evidence

    20 Mar 2012 JUSTICE MANSFIELD (PRESIDENT), MR GF LATTA (MEMBER), MR R STEINWALL (MEMBER)

  9. Application by DBNGP (WA) Transmission Pty Ltd [2012] ACompT 6
    ACT 2 of 2012

    15 Mar 2012 JUSTICE MANSFIELD (PRESIDENT), MR R DAVEY AND PROFESSOR D ROUND

  10. Application by APT Allgas Energy Limited (No 2) [2012] ACompT 5
    ACT 5 of 2011

    11 Jan 2012 MANSFIELD J (PRESIDENT), MR R DAVEY, PROFESSOR D ROUND

  11. Application by Envestra Limited (No 2) [2012] ACompT 4
    ACT 6 of 2011

    APPLICATION UNDER S 245 NATIONAL GAS LAW – review of full access arrangement decision of Australian Energy Regulator – whether building blocks of allowable revenue correctly determined (1) Debt risk premium – reliability of fair value curve – whether regulator tested fair value curve appropriately – whether all relevant material considered – where …

    11 Jan 2012 MANSFIELD J (PRESIDENT), MR R DAVEY, PROFESSOR D ROUND

  12. Application by Envestra Ltd (No 2) [2012] ACompT 3
    ACT 7 of 2011

    APPLICATION UNDER S 245 NATIONAL GAS LAW - review of full access arrangement decision of Australian Energy Regulator - whether building blocks of allowable revenue correctly determined regarding: (1) Debt risk premium - reliability of fair value curve - whether regulator tested fair value curve appropriately - whether all relevant material…

    11 Jan 2012 MANSFIELD J (PRESIDENT), MR R DAVEY, PROFESSOR D ROUND

  13. Application by SPI Electricity Pty Limited [2012] ACompT 2
    ACT 7 of 2010

    6 Jan 2012 FOSTER J (DEPUTY PRESIDENT), MR G LATTA AM AND PROFESSOR D ROUND

  14. Application by United Energy Distribution Pty Limited [2012] ACompT 1
    ACT 6 of 2010 ; ACT 7 of 2010 ; ACT 8 of 2010 ; ACT 9 of 2010 ; ACT 10 of 2010

    6 Jan 2012 JUSTICE FOSTER (DEPUTY PRESIDENT), MR G LATTA AM AND PROFESSOR D ROUND